We carry out the complete design for the new drainage treatment plant located on the surface of the Magdalena mine to prevent the water raft from crashing.

Said Plant is formed by a decanter that allows to dump “quasi-clean” water in the corresponding raft and a lung tank together with the corresponding pumping system and pipes that allows the sludge to be taken to the corresponding treatment plant and act as a lung when the decanter It clogs up.

With this project we managed to eliminate the bottleneck that involved the clogging of the drainage water basin allowing continuous work flow. Developing the entire water distribution network differentiating raw water from dyed waters.